The Township of Upper Providence has scheduled milling and resurfacing work for the following roads as part of the 2025 Road Program.
Phase 1 & 2: September 2–5, 2025
- Spring Hunt Lane (North Providence to Cul-de-Sac)
- White Tail Lane (Spring Hunt Lane to Cul-de-Sac)
- Cove Lane (North Providence Road to #108/#111 Cove Lane)
- Cove Lane (#108/#111 Cove Lane to Cul-de-Sac)
- Dale Road (Hillendale Road to Cul-de-Sac)
- Hillendale Road (Ridley Creek Road to Subdivision Roadway)
Phase 3: September 8–16, 2025
- School Lane (North Providence Road to First Avenue)
- First Avenue (Ray Roche Park to Rose Tree Office Campus)
- Evans Avenue (North Providence Road to Dead End)
- Maple Avenue (North Providence Road to Dead End)
- Second Avenue (Sandy Bank Road to Evans Boulevard)
- Dash Avenue (Valley View Road to Dead End)
- Pickering Lane (Dash Avenue to Old State Road)
- Old Mill Drive (State Road to Cedar Meadow/Hill Lane)
- Dogwood Road (Farnum Road to Circle)
- Farnum Road (Seam at Farnum Road Repair to Speed Hump at #675 Farnum Road)
Resident Reminders
- Please remove all vehicles from the street by 7:00 a.m.
- Residents will be able to access their homes, but traffic may be restricted and street parking will be prohibited until the work is completed.
- Please do not drive through barricades, as they are placed for safety and worker protection.
- Avoid driving or walking across freshly tarred or paved streets. Oils and tar can stain cars, clothes, carpet, and other materials.
- If work is not completed on the scheduled date, it will continue on the following day.
- No work will be performed on weekends.
Thank you for your cooperation. Remember: this is only a short-term inconvenience for a better road!